OCTOBER 2026
On Sunday, October 11, crews completed the installation of a massive reinforcing steel cage for a new straddle bent along S.R. 836. Weighing about 127,000 pounds and measuring 130 feet long, the cage was carefully lifted by cranes and lowered into the formwork.
To complete this complex operation safely, crews brought in about 30 truckloads of material to build and level a stable working pad on the roadway for the cranes. The successful installation marks another important milestone in constructing the new double-decked S.R. 836 roadway.
Check out the video for a closer look at this impressive operation.
CONCRETE POUR ADVANCES THE NEW S.R. 836 DOUBLE-DECKED ROADWAY WEST OF THE MIAMI RIVER
OCTOBER 2026
The video shows crews completing a major concrete pour on October 3, for the new double-decked S.R. 836 roadway just west of the Miami River. The operation used one concrete pump and approximately 60 concrete trucks to place 590 cubic yards of concrete — roughly 2.4 million pounds — as crews continue advancing construction of the new elevated roadway.
AUGUST 2026 COMMUNITY OUTREACH POP-UP EVENTS
SEPTEMBER 2026
Throughout August, the I-395/S.R. 836/I-95 Design-Build Project Team was out in the community, connecting with residents, businesses and visitors at pop-up outreach events across the project area. This video highlights the month’s outreach activities through photos of the team sharing project updates, answering questions and connecting with the community.
Want to meet the project team at an upcoming event? Visit our Events page for information on future community outreach opportunities.
CONCRETE POUR FOR THE WESTBOUND I-395 SIGNATURE BRIDGE SUPERSTRUCTURE
SEPTEMBER 2026
Construction continues to advance on the westbound I-395 Signature Bridge superstructure, with crews installing reinforcing steel, formwork, and post-tensioning ducts and placing concrete for the massive box-girder deck. The post-tensioning system will add strength as the deck is constructed and work with the bridge’s arches and stay cables to support the completed superstructure. Recent concrete operations have included pours for the deck, webs, and diaphragms that make up the box girder. The video shows one of the largest concrete pumps in the country in action during a recent pour on the westbound Signature Bridge superstructure. As work progresses, these sections are coming together to form the new westbound I-395 roadway.
SIGNATURE BRIDGE CONSTRUCTION FROM ABOVE
SEPTEMBER 2026
This drone video offers an aerial view of ongoing construction on the I-395 Signature Bridge. Arches 1, 2, 4, and 5 are closed, while crews continue work on the first of three cast-in-place structural elements for each of the two remaining arches, 3 and 6. Other work shown includes the installation of falsework, formwork, and reinforcing steel, along with concrete pours for the westbound Signature Bridge superstructure, which will ultimately be supported by the arches and stay cables.
MAJOR MILESTONE ACHIEVED AT SIGNATURE BRIDGE ARCH #6
JULY 2026
The project team recently reached another major milestone with the successful completion of the foundation pour for Signature Bridge Arch #6, located adjacent to the Phillip and Patricia Frost Museum of Science. This was the second-largest concrete and most complex foundation pour of the entire project and represents a significant step toward construction of one of the two remaining arches.
The foundation measures 120 feet long, 50 feet wide, and 16 feet deep, and required approximately 3,672 cubic yards of concrete, delivered by 408 concrete trucks, placed by four concrete pumps (with a fifth on standby). To ensure the concrete cures properly, crews installed an advanced cooling system consisting of more than 30,000 feet of tubing circulating chilled water from a large industrial chiller, with a backup chiller on site for redundancy.
STRADDLE BENT FORMWORK ERECTED
JULY 2026
The time lapse video shows the successful erection of formwork for the final straddle bent support structure, which will span the full width of eastbound S.R. 836. The formwork measures 134 feet long and weighs approximately 266,000 pounds. The operation required two heavy-lift cranes and the delivery of approximately 26 truckloads of limerock to construct a temporary crane pad. Once the work was complete, the material was removed, the roadway was cleaned, and all lanes were reopened to traffic. The next step in constructing the straddle bent will involve assembling and installing a reinforcing steel cage in preparation for the concrete pour.
ANOTHER MILESTONE ACHIEVED – COMPLETION OF THE INSTALLATION OF ALL PRECAST ARCH # 4 SEGMENTS
MAY 2026
On Friday, May 15, the project team completed the installation of all 65 precast arch segments for Arch #4 that soars 252 feet over Biscayne Boulevard. Each segment is unique and weighs approximately 90 tons.
INSTALLATION OF 90-TON PRECAST ARCH SEGMENT
AUGUST 2025
Crews carefully erect one of 65 precast arch segments that will form one of the six soaring arches of the I-395 Signature Bridge, a new Miami landmark in the making. A total of 345 precast arch segments will be used to complete all six arches.
AUGUST 2025 MONTHLY STAKEHOLDER MEETING
AUGUST 2025
I-395/S.R. 836/I-95 Project Monthly Stakeholder Meeting.
CONNECTING MIAMI – BY THE NUMBERS: EPISODE 1
AUGUST 2025
At the heart of the Signature Bridge is a massive structure — the center pier where all six iconic arches converge. Watch our debut episode, as we take you behind the scenes to explore the engineering marvel that anchors this Miami landmark.
ENGINEERING & PUBLIC WORKS ROADSHOW KICKED OFF 2025 TOUR AT MIAMI’S SIGNATURE BRIDGE
FEBRUARY 2025
The Engineering and Public Works Roadshow launched its 2025 tour on Friday, February 14, at the foot of Miami’s Signature Bridge construction site. The Roadshow stop included remarks from FDOT District Six Secretary Stacy Miller and executives from the American Council of Engineering Companies (ACEC), the American Public Works Association (APWA), and the American Society of Civil Engineers (ASCE). They were joined by representatives from local elected officials, as well as the engineers and public works professionals who are making the project possible.
WESTBOUND I-395 TRAFFIC SHIFT
DECEMBER 2023
On THURSDAY MORNING, DECEMBER 21, a new traffic pattern will be implemented on westbound I-395 to open new bridges and continue the construction of the new I-395 that will enhance safety, mobility, and access.
EASTBOUND S.R. 836/I-395 TRAFFIC SHIFT
NOVEMBER 2023
On FRIDAY MORNING, DECEMBER 1, a new traffic pattern was implemented on S.R. 836/I-395 to open new bridges and continue the construction of the new I-395 that will enhance safety, mobility, and access.
NEW TRAFFIC PATTERN FOR NORTHBOUND I-95 DRIVERS HEADING TO EASTBOUND I-395
OCTOBER 2023
On WEDNESDAY MORNING, OCTOBER 25, a new traffic pattern was implemented for drivers on northbound I-95 heading to eastbound I-395 to open newly constructed bridges. Electronic message boards and other signage will is in place to alert drivers to the new pattern.
INSTALLATION OF ARCH SEGMENTS FOR THE I-395 SIGNATURE BRIDGE
JULY 2022
Installation of a precast arch segments for one of the six arches that will part of the signature bridge. A total of 345 precast arch segments will be erected for the six arches.
STATE ROAD (S.R.) 836 BRIDGE CAP SEGMENT AND BEAM LIFTER
JUNE 2022
The S.R. 836 bridge cap segment and beam lifter started operations on Tuesday evening, June 28. The 480-foot-long lifter or gantry was specifically designed to install bridge cap segments and beams for this project. To complete the new S.R. 836 double decked roadway, the lifter will erect 145 bridge cap segments and 363 bridge beams. Each cap segment weighs just over 90 tons and the bridge beams range in length from 100 feet to 190 feet. To view an animated video of the lifter in action, please click below.
NEW TRAFFIC PATTERN ON THE WESTBOUND I-395 RAMP TO NORTHBOUND I-95
SEPTEMBER 2021
TUESDAY MORNING, SEPTEMBER 28 – The ramp from westbound I-395 to northbound I-95 will be closed and traffic will be shifted to a temporary single-lane ramp on the left side of the road. Variable Message Signs (VMS) will direct drivers going west on I-395 who want to go north on I-95 to the new temporary ramp.
NORTH BAYSHORE DRIVE RAMP CLOSURE
SEPTEMBER 2021
The North Bayshore Drive ramp to eastbound MacArthur Causeway will be permanently closed on Thursday morning, September 2, to continue foundation work for the new I-395 Signature Bridge and the construction of the new permanent ramp.
CONCRETE POUR FOR THE SIGNATURE BRIDGE CENTER PIER FOOTER
JULY 2021
On Sunday morning, July 25, the contractor completed the concrete pour for the Signature Bridge center pier footer. The operation took approximately 33 hours to complete and involved 550 trucks delivering concrete to the site with four concrete pump trucks working continuously to place the concrete into the footer. To view a time lapse video of the operation click below.
SEGMENTAL LIFTER
APRIL 2021
Time-lapse video of the segmental lifter being placed onto a bridge currently under construction. The segmental lifter will be used to erect bridge segments over the FEC rail tracks located adjacent to NW 1 Avenue.
SEGMENT LIFTER AT WORK
MAY 2021
Time lapse video of the segment lifter erecting a bridge segment adjacent to the Brightline/FEC tracks for the new I-395.
CONTINUOUS NORTHBOUND I-95 LANE CLOSURE
SEPTEMBER 2020
Starting on Wednesday morning, September 9, one outside northbound I-95 lane will be continuously closed from south of NW 14 Street to north of NW 17 Street for a period of approximately three weeks.
PROJECT PRESENTATION
SEPTEMBER 2023
The I-395/S.R. 836/I-95 Project is a partnership between the Florida Department of Transportation (FDOT) and (GMX).
SEGMENT INSTALLATION
JUNE 2020
The installation of bridge segments has started for the new westbound I-395 segmental bridges.