NIGHTTIME CONCRETE POUR ADJACENT TO NE 2 AVENUE AND I-395

On Friday evening, November 21, the project contractor will conduct a concrete pour at one of the signature bridge arch foundations located west of NE 2 Avenue, adjacent to I-395, as shown above. The concrete pour will begin at 11 p.m. and continue until approximately 11 a.m. on Saturday, November 22. Every effort will be made to minimize noise as much as possible; however, nearby residents and businesses may experience periods of higher-than-normal noise levels. No lane closures will be required for this operation.