CLOSURES ON BISCAYNE BOULEVARD, NE 13 STREET, AND NORTH BAYSHORE DRIVE FOR DRAINAGE WORK AND CONCRETE POUR
- Friday, October 24 – Beginning at 11 p.m. Friday, October 24, through 6 a.m. Saturday, October 25, the following full closures will be in place for drainage improvements and a concrete pour:
- Biscayne Boulevard – All northbound and southbound lanes from NE 14 Street to NE 11 Terrace
- NE 13 Street – All lanes from North Bayshore Drive to NE 2 Avenue
- North Bayshore Drive – All southbound lanes from NE 14 Street to NE 13 Street

Saturday, October 25 – At 6 a.m., the full closures will be lifted, and the lane closures noted below and shown above will remain in place until 4 p.m. to safely complete the concrete pour at the arch foundation:
- One right lane closed on northbound Biscayne Boulevard from NE 11 Terrace to NE 13 Street
- One left lane closed on NE 13 Street from North Bayshore Drive to Biscayne Boulevard
This operation will involve approximately 220 concrete truck deliveries and four concrete pumps working continuously to form a watertight seal at the foundation, allowing crews to continue arch construction safely.
🚧 Please use caution when driving near the area as large trucks will be entering and exiting the work zone throughout the operation.