SATURDAY SHEET PILE DRIVING OPERATIONS ADJACENT TO THE BISCAYNE BOULEVARD RAMP TO EASTBOUND MACARTHUR CAUSEWAY

On Saturday morning, August 23, the contractor will begin installing steel sheet piles next to a Metromover pier at the location shown above. This work is being coordinated with the Miami-Dade County Department of Transportation and Public Works and is scheduled to take place during periods when the Metromover system is offline for upgrade activities. Sheet pile installation on August 23 and the subsequent Saturdays below will occur between 7 a.m. and 1 p.m.
- Saturday, August 23
- Saturday, September 13
- Saturday, September 21
- Saturday, October 11
- Saturday, October 25
- Saturday, November 8
- Saturday, November 22
- Saturday, December 6
- Saturday, December 20
The work is necessary to relocate an existing Metromover Pier to allow for the widening of the roadway. Every effort will be made to minimize noise as much as possible; however, nearby residents and businesses may experience periods of higher-than-normal noise levels. No lane closures will be required for this operation.