RESCHEDULED: EXTENDED FULL CLOSURE OF EASTBOUND S.R. 836 AT NW 17 AVENUE AND TEMPORARY CHANGE TO DRAWBRIDGE OPERATING SCHEDULE The previously scheduled operation to install a reinforcing steel…
Crews completed a major concrete pour this weekend for the new double-decked S.R. 836 roadway just west of the Miami River. The operation used one concrete pump and approximately…
EXTENDED FULL CLOSURE OF EASTBOUND S.R. 836 AT NW 17 AVENUE AND TEMPORARY CHANGE OF DRAWBRIDGE OPERATION SCHEDULE Friday, October 2 through Saturday, October 3 – All eastbound S.R.…
WHAT IS A MECHANICALLY STABILIZED EARTH WALL (MSE)? As shown in the photos below, an MSE wall, is being constructed to support the westbound roadway as it transitions from the…
EXTENDED FULL CLOSURE OF EASTBOUND S.R. 836 AT NW 17 AVENUE AND TEMPORARY CHANGE OF DRAWBRIDGE OPERATION SCHEDULE Friday, October 2 through Saturday, October 3 – All eastbound…
CLOSURE OF THE NW 17 AVENUE RAMPS TO WESTBOUND S.R. 836 To view a map of the detours please click here. WEEKEND DAYTIME S.R. 836 LANE CLOSURES Saturday, September…
Construction continues on the new higher-capacity I-395 mainline linking the I-395 signature bridge with I-95 and S.R. 836. The photos above show crews erecting massive precast roadway segments,…